MIRAMAR INFRASTRUCTURE IMPROVEMENTS & SERVICE CONVERSIONS, PHASE III
LOCATION
Miramar, FL
OWNER/CLIENT
City of Miramar
COST
$6M (Initial Estimate $8M)
COMPLETION
2020
- Civil Engineering Analysis & Design
- New Water Distribution System Mains
- New Water Meter Boxes
- As-Built Drawings
- Utility Coordination
- Permitting
- Interagency Coordination
- Construction Phase Engineering & Inspection Services
- Roadway Resurfacing & Reconstruction
- Signage & Street Markings
- Horizontal Directional Drilling
- Construction Contract Administration
- Construction Submittal
The Miramar Infrastructure Improvements and Service Conversions, Phase III project involved the design and construction oversight of over 72,000 LF of residential water main, including a 100 LF horizontal directional drilling operation. The design included a new 6-inch PVC and DIP water main, new water services, new water meter boxes and service connections, and complete roadway restoration. The roadway restoration includes a full depth trench restoration, edge of pavement to edge of pavement milling, and a final overlay, and complete striping for each street.
During our design effort, we realized that the City lacked accurate and complete as-builts for the sanitary sewer system. As part of our effort, we provided all sanitary sewer details to the City GIS department to allow them to update their utility records.